If during a schedule update, the critical path changed, this can be attributed to

If during a schedule update, the critical path changed, this can be attributed to

 

If during a schedule update, the critical path changed, this can be attributed to

A change in the logic.
A change in the calendar of some activities.
A near-critical path became longer than the previous critical path.
All of the other answers.
The critical path became shorter than a near-critical path.

 