Which of the following statements are true?

Which of the following statements are true?

 

1- You are in the process to create project schedule for repainting your house, you first need to scrap off the existing paint, and then add a layer of primer. The primer provides the paint a better bonding surface so it sticks to the base material much better. Without priming, drywall surfaces will soak up more finish paint in some areas than in others, producing a splotchy effect.

Unfortunately, you have to wait once the primer is applied you must wait until the primer dries before adding on the actual paint. You estimate that it will take 8 hours for the primary to dry. To correctly sequence these activities, which of the following should you do?

Question options:

Add a lag time 8 hours to the priming task
Add a lead time of 8 hours to the priming task
Add float time between the priming and painting tasks
Fast track the priming and painting tasks

2-

You are the project manager at a software company developing the next-gen OODBMS (Object Oriented Data Base Management System). You are in the process of developing project schedule using CPM (Critical Path Method). One of the disadvantages of CPM is that it does NOT consider resource availability. In fact, you’ve quickly identified that one of your key engineers, Michael, is over allocated. Which of the following statements are true?

Question options:

You should use crashing in order to resource level the critical path tasks
You should use three point estimates in order to reassign the resource appropriately
You should use resource leveling heuristics to reassign the resource appropriately
You should fast track the process in order to resource level the critical path tasks.

3-

You’ve been hired as manager to design and construct a new casino in Las Vegas, over the next 18 months. Given the size of the project and the abbreviated time frame, you are attempting to identify ways to reduce the timeframes for many of various tasks. You’ve developed the WBS and created a Gantt chart using specialized scheduling software.

After analyzing the data, you’ve discovered several opportunities where tasks and phases may be overlapped in order to save time. This is an example of:

Question options:

Progressive elaboration
Resource elaboration
Fast tracking
Crashing and schedule

4-You are in the process to create a project schedule for repainting your house, you first need to scrap off the existing paint, and then add a layer of primer. The primer provides the paint a better bonding surface so it sticks to the base material much better. Without priming, drywall surfaces will soak up more finish paint in some areas than in others, producing a splotchy effect.

You decided to speed up the process by starting priming before all the scraping is finished. To correctly sequence these activities, which of the following should you do?

Question options:

Add float time between the priming and painting tasks
Fast track the priming and painting tasks
Add lag time to the priming task
Add lead time to the priming task

 

Which of the following statements are true?

Which of the following statements are true?

Which of the following statements are true?

 

"Get yourself this Paper or a similar one at an unbeatable discount!"

"Order a similar paper and get 15% discount on your first order with us
Use the following coupon
"FIRST15"

Order Now